CONSTRUCTION THANA CITY

Updated: Dec 20, 2019

- Start work construction 2019.10.11

set line furniture to worker and detail on site



- Set leveling floor and prepare furniture in factory



- Update work construction 2019.10.18

- installation air condition and prepare main water

- prepare work for install tile

- setting leveling floor complete and paint waterproof concrete before install tile


- Update work construction 2019.10.25 - Prepare work furniture in factory - Setting line wall for furniture and wall some part



- Update work construction 2019.11.1

- Installation pipe air system

- Installation electrical wire and main electrical - Install work build in some part - Install pipe for water system - Ceiling Some part - Prepare work for install Aluminium window






- Update work construction 2019.11.15 - Install Ceiling Some part

- Support door slide - Change aluminium door and window


- Update work construction 2019.12.13 - Install Furniture

- Paint ceiling


- Update work construction 2019.12.20 - Spray Paint furniture

- Paint ceiling

- Prepare Laminate floor